Introduction:

The Masterclass Slideline M series is a selection of wall units which utilise a sliding door feature. They come complete with pre-installed LED spot lighting with PIR sensor and glass shelving.

The unit is available in heights from 288mm to 720mm and widths from 1000mm to 2000mm. Units can also be connected together should it be required.

The following pages will show important points to be aware of when planning this unit, followed by fitting instructions to help assemble the unit.

As the Slideline M is fitted with an LED spot light system with PIR sensor and driver as standard, please ensure there is a suitable mains (240v) power supply available for the installation.

Please be aware this unit is supplied partially built. Please ensure that you have prepared an area large enough for the assembly process.

Safety Notice:

Be aware that assembled units can be heavy. We recommend two person handling during assembly of this product.

Due to the size of the completed units it is suggested that it is assembled in an area as close as possible to the final installation location.

Ensure the intended assembly area is clear of trip hazards and that pets and young children are at a safe distance.

During assembly use a soft object such as a blanket to rest panels on to prevent damage to the show surfaces.

Tools Required:

Tape Measure Hammer Spirit Level Screwdrivers Hammer Drill (Wall Brackets)

Components Supplied (per unit):

Each unit will be supplied with the necessary fixings and fasteners to fully assembly the unit. Please check you have the required quantity before proceeding with the assembly.

Wall Mounting Plates x 2

Rear Glass Shelf Pegs x 24

Outer Wrap Panels - 1 Set (Top & Bottom panels should be identified)

Inner Cabinet Assy CW LEDs & PIR Sensor x 2

Doors CW Runners - 2 Sets

Assembly

Step 1 - Mounting Inner Cabinets:

Using suitable expanding wall fasteners fix the mounting plates (x4) ensuring the spacing dimensions and level are correct to hang the cabinets.

Hang the cabinets one at a time and adjust the the mounting brackets so that the cabinets are perfectly level and the sides (cheeks) of the cabinets are parallel and touching.

There should be no steps or gaps between the adjoining edges. when properly adjusted.

Lock the brackets in place as outlined below.

1 - Height Adjustment Screw

To align both cabinets vertically use this screw. Clockwise lifts the cabinet and anti-clockwise lowers it.

Fit Cover After Adjustment

2 - Depth Adjustment Screw

1

To align the front edges of the cabinets use this screw. Clockwise will pull the cabinet toward the wall and anti-clockwise will push the cabinet away from the wall.

2

3

3 - Lock - Unlock Screw

View of inside top corners

Once all adjustment have been completed use this screw to secure the cabinet to the wall bracket. Clockwise will lock the cabinet into position and anti-clockwise will enable the cabinet to be lifted away from the wall.

Assembly

Step 2 - Fitting Shelves:

Using the supplied shelf pegs, push-fit into the pre-drilled holes in the areas circled below. Fit the pegs at the desired height - all must be at the same level for each individual shelf.

When fitting shelves, ensure they are located correctly, inside the shelf pegs and not rested on top.

See below:

Assembly

Step 3 - Fitting Outer Wrap Panels:

The outer wrap panels are cut to size for each order.

Uneven fitting surfaces may require the wrap panels to be scribe cut to ensure correct alignment at the front of the assembly.

Before fitting the outer wrap panels please take note of the details below.

The panels should be identified as top or bottom. If they are not identified as such they can be identified by the type of rail inserts.

As shown below the longer rail inserts identify the bottom panel and the small (short) inserts identify the top panel.

Rail Insert Positions

TOP

x 2 - Front and rear rail.

x 2 - Front and rear rail.

Rail Inserts

x 2 - Front and rear rail.

BOTTOM

x 2 - Front and rear rail.

Assembly

We recommend fitting the two side panels first (A). Using 1¼” x 8 screws. These should be fastened through the inner cabinet into the outer wrap panel. They should be centred against the side panels of the interior units, leaving a 19mm overlap top and bottom.

B

Door running rails to the front.

A

A

B

Centrelines of door rails.

CL

CL

When fitting the top and underside panel the front faces of these panels MUST be vertical when a level is placed against both of them simultaneously. This is to ensure the door running rails are also vertical to enable them to operate smoothly.

View through the side.

Assembly

Step 4 - Fitting Doors:

The doors will be pre-fitted with the runner assemblies.

The bottom door guide damper should be ‘pre-loaded’ before fitting the door.

Simply push the bottom catch towards the main runner wheels as shown in the images below.

Assembly

View through the side.

Locate lower runners into rail.

Locate the bottom runners of the first door into the back rail (above).

Unlock the top runner (both sides) by operating the small yellow tab as shown below.

Pull down on the lugs each side as shown and move the door to an upright position and let the guide wheels on the runners spring back into the top rail by releasing the lugs.

Lock the yellow tab back into position.

Repeat the process for the other door but use the front rails.

Yellow Locking Tab.

Un-locked Position.

Locked Position.

Lift Tab.

Pull the lug down.

Assembly

Assembly Complete

The assembly is now completed. Connect the mains supply and check the LED units.

Adjustment instructions can be found on the next page.

Assembly

Vertical Adjustment

Unlock the top runners (both sides) by operating the small yellow tab as shown below.

Use a size 3 allen key on the lower runners to adjust the vertical position of the door.

Lock the yellow tabs back into position.

Ensure the top runners are in the un-locked position.

Make adjustments on the lower runners

Return the top runners to the locked position.

Assembly